Pre-Construction
Protection Report
Kitchen & Main-Floor Renovation
This is an illustrative sample for a fictional Toronto kitchen and main-floor renovation. It shows the structure and depth of the report — the figures and project are for demonstration only. Your report is prepared specifically for your renovation.
Kitchen & Main-Floor Renovation
Bowlexis was engaged to provide independent pre-construction review of a planned kitchen and main-floor renovation, ahead of contractor selection. The report defines the scope of work, establishes a staged payment framework, and sets out a change-order control process — giving the owner a documented basis before any commitment.
Key findingsExisting conditions were captured by LiDAR scan. Key measured dimensions are shown below; the full measured drawing is issued separately (ref. MD-01).
| Kitchen | 3.65 m × 4.20 m (15.3 m²) |
|---|---|
| Dining / main floor | 4.10 m × 5.05 m (20.7 m²) |
| Ceiling height | 2.64 m |
| Existing opening (kitchen ↔ dining) | 1.80 m |
| Main-floor windows | 4 |
| Milestone | Release trigger | % |
|---|---|---|
| Mobilization | Engagement signed, materials ordered | 10% |
| Demolition complete | Site stripped and inspected | 15% |
| Rough-in | Electrical & plumbing rough-in passed inspection | 25% |
| Cabinetry & millwork | Installed and verified | 25% |
| Finishes | Flooring, tiling, and paint complete | 15% |
| Substantial completion | Deficiencies cleared, final walkthrough | 10% |
Subject to statutory holdback under the Construction Act (Ontario). Releases are tied to observable progress, not calendar dates.
All changes to the defined scope are documented, priced, and approved in writing before work proceeds. No verbal variations.
| CO # | Description | Cost impact | Status |
|---|---|---|---|
| CO-01 | Upgrade island worktop to stone | + $2,400 | Approved |
| CO-02 | Additional pot lights (× 4) | + $680 | Approved |
| CO-03 | Relocate radiator (owner request) | TBC | Pending pricing |
| Item | Note | Rating |
|---|---|---|
| Concealed conditions | Unknown behind existing kitchen wall until demolition. | |
| Permit timing | City approval may affect the start date. | |
| Appliance lead times | Owner-supplied items may delay final fit-out. | |
| Holdback compliance | Statutory holdback to be retained throughout. |
This is an illustrative sample created to show the structure and depth of a Pre-Construction Protection Report. It does not represent a real project, client, or property, and the figures shown are for demonstration only. Your report is prepared specifically for your renovation, scope, and decisions.
Book a consultation and we will confirm the right tier and what your Protection Report should cover, before you hire, sign, or pay.